Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 77111 REL 17: 1995-057-02 EXP SOUTHERN IDAHO WILDLIFE MITIGATION
Project Number:
Title:
Shoshone-Bannock Wildlife Mitigation Projects
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Upper Snake Snake Upper 100.00%
Contract Number:
77111 REL 17
Contract Title:
1995-057-02 EXP SOUTHERN IDAHO WILDLIFE MITIGATION
Contract Continuation:
Previous: Next:
77111 REL 7: 1995-057-02 EXP SOUTHERN IDAHO WILDLIFE MITIGATION
  • 77111 REL 27: 1995-057-02 EXP SOUTHERN IDAHO WILDLIFE MITIGATION
Contract Status:
Closed
Contract Description:
This contract is a continuation of the Shoshone-Bannock Tribes (SBT) SIWM program. Work under the FY19 contract will build on the work completed in FY18.

Major Work Elements for FY 2019 include:

1.  Riparian restoration efforts at Legacy Springs
2.  Vegetation maintenance at Legacy Springs
3.  Vegetation maintenance at Bannock Creek
4.  Russian olive removal at Legacy Springs
5.  Russian olive removal at Bannock Creek
6.  Infrastructure maintenance
7.  Fence reconstruction at Cinder Cones
8.  Revise Management Plan
     a.  Revise Plan to meet ISRP concerns and meet LMP template
     b.  Complete Cinder Cones chapter
     c.  Revise monitoring plan to meet ISRP concerns
Account Type(s):
Expense
Contract Start Date:
04/01/2019
Contract End Date:
03/31/2020
Current Contract Value:
$416,142
Expenditures:
$416,142

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. Administration of BPA contracts 03/31/2020 03/31/2020
Receipt of EC documentation/clearance from BPA C: 165. Satisfy environmental compliance requirements 03/31/2020 03/31/2020
Coordinate project lands management with relevant land agencies D: 191. Coordinate project lands management with relevant land agencies 03/31/2020 03/31/2020
Identify potential mitigation properties E: 114. Identify potential mitigation properties 03/31/2020 03/31/2020
Develop and implement Legacy Springs riparian vegetation restoration efforts G: 47. Plant Vegetation- Legacy Springs riparian 03/31/2020
Maintain vegetation on project lands- Bannock Creek H: 198. Maintain vegetation on project lands- Bannock Creek 10/15/2019 10/15/2019
Maintain vegetation on project lands- Legacy Springs I: 198. Maintain vegetation on project lands- Legacy Springs 10/15/2019 10/15/2019
Russian olive removal- Bannock Creek J: 199. Russian olive removal- Bannock Creek 03/31/2020 03/31/2020
Russian olive removal- Legacy Springs K: 199. Russian olive removal- Legacy Springs 03/31/2020 03/31/2020
Maintain program infrastructure L: 186. Maintain program infrastructure 03/31/2020 03/31/2020
Lease agricultural lands- Legacy Springs M: 194. Administer agricultural Lease- Legacy Springs 03/31/2020 03/31/2020
Lease agricultural lands- Lavaside N: 194. Administer agricultural Lease- Lavaside 03/31/2020 03/31/2020
Develop, install, and maintain public access information O: 188. Provide public access information 03/31/2020
Complete vegetation monitoring plan P: 174. Develop vegetation monitoring plan 03/31/2020
Revised Management Plan Q: 193. Revise Management Plan 03/31/2020
Completed bi-Annual Report for April 2018 to March 2020 R: 132. Submit 2-yr Progress Report for the period April 2018 to March 2020 03/31/2020
Completed Annual Report S: 132. Submit 2yr Progress Report for the period April 2013 to March 2015 10/30/2019 10/30/2019
Completed Annual Report T: 132. Submit 2-yr Progress Report for the period April 2016 through March 2018 03/31/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 2 instances of WE 198 Maintain Vegetation
  • 2 instances of WE 199 Remove Vegetation
  • 1 instance of WE 193 Produce Land Management Plan
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 04/01/2019
B 119 Administration of BPA contracts 04/01/2019
C 165 Satisfy environmental compliance requirements 04/01/2019
D 191 Coordinate project lands management with relevant land agencies 04/01/2019
E 114 Identify potential mitigation properties 04/01/2019
F 172 Conduct pre-acquisition activities- Brown property and potential additional properties 04/01/2019
G 47 Plant Vegetation- Legacy Springs riparian
H 198 Maintain vegetation on project lands- Bannock Creek
I 198 Maintain vegetation on project lands- Legacy Springs
J 199 Russian olive removal- Bannock Creek 02/07/2019
K 199 Russian olive removal- Legacy Springs 02/07/2019
L 186 Maintain program infrastructure 10/16/2019
M 194 Administer agricultural Lease- Legacy Springs
N 194 Administer agricultural Lease- Lavaside
O 188 Provide public access information
P 174 Develop vegetation monitoring plan 02/07/2019
Q 193 Revise Management Plan
R 132 Submit 2-yr Progress Report for the period April 2018 to March 2020 04/01/2019
S 132 Submit 2yr Progress Report for the period April 2013 to March 2015 04/01/2019
T 132 Submit 2-yr Progress Report for the period April 2016 through March 2018 04/01/2019